Details

Project Type
Office Fit-out

Duration
28 Weeks

Size
40,000 Sq Ft

 

 

 

Maclay Murray & Spens

St. Vincent Street and Bothwell Street, Glasgow

GHI were appointed to fit out the Glasgow offices of this prestigious firm of solicitors having previously completed projects for them in London and Edinburgh.

Working with the design team, we played a ‘hands on’ role from the early stages, ensuring buildability and cost certainty within challenging timescales.

The works involved the extensive refurbishment of 3 floors in the Glasgow Headquarters whilst the client was still in residence. Detailed phasing of the works was critical to guarantee both business continuity and to ensure a safe working environment for its occupants was maintained at every stage of the project.

The completed project included all executive suites, meeting rooms, offices and toilets.

“We continue to be impressed by the consistent high standards of workmanship and project management achieved by GHI in a number of challenging jobs, which they have undertaken for us in several UK city locations”.

Michael J. Walker
Chairman
Maclay Murray & Spens