Details
Project Type
Refurbishment
Duration
Ph. 1 - 8 Weeks
Ph. 2 - 16 Weeks
Ph. 3 - 16 Weeks
Size
Ph. 1 - 8600 Sq.ft
Ph. 2 - 25800 Sq.ft
Ph. 3 - 19400 Sq.ft
The Scottish Government
Saughton House, Edinburgh
Following a long history of working directly for the Scottish Government at Saughton House, GHI has been awarded all three phases of the current refurbishment programme, each separately and competitively tendered.
Working with Space Solutions and Mitie Technical Facilities Management, GHI have delivered Phases 1 & 2 to the client ahead of programme, with Phase 3 on target for a similarly reduced programme time.
Phase 1 2 spurs 8 week programme - completed 8 weeks.
Phase 2 6 spurs 22 week programme - completed 16 weeks.
Phase 3 5 spurs 22 week programme - projected 16 weeks.
The spurs (as the distinctive Saughton House wings are named) are each completely stripped out and then refurbished as modern workspaces with full M & E services, glazed offices, suspended ceilings, flooring and decoration. This work, to approx 54.000 sqft of accommodation, has been carried out during normal working hours, in a fully occupied, working building and in adherence with The Scottish Government’s stringent security regime.