140 West George Street, Glasgow

140 West George Street, Glasgow

Project: Building Refurbishment
Programme: 12 Weeks
Consultants: TFT, Cooper Cromar

The GHI team carried out the refurbishment of the existing Legal and General building in the city centre.

The first phase of the project involved a refresh of the reception area, lower ground level and the third floor.

The scope for the ground level works involved the complete strip out of offices, lift lobby cores and washroom facilities and the formation of changing and showering facilities.

There was a high M&E element with full replacement of services and shutdowns involved. The project was undertaken in a live environment as areas of the building remained operational throughout the works.