West Dunbartonshire Council, Bridge Street, Dumbarton

West Dunbartonshire Council, Bridge Street, Dumbarton

Project: Office Refurbishment
Programme: 30 Weeks
Consultant: Michael Laird Architects

GHI carried out a full refurbishment across three floors for West Dunbartonshire Council, which would home 280 staff members.

As part of the Council’s Office Rationalisation Project, GHI were appointed to refurbish the Bridge Street office to a similar standard provided by them at the recently completed WDC office fit-out at Aurora House, Clydebank.

GHI were required to submit a proposal of work to develop the design brief and tender the design proposal for the successful refurbishment of the building.

GHI proposed a 2 phase approach to the construction works to allow continued occupation of the ground floor main office. Phase 1 consisted of the upper floors and part ground floor was completed in 14 weeks and phase 2 in 8 weeks. GHI successfully completed the works over a 30 week programme.

Generally, a full strip out of MEP services, partitions (stud and masonry), ceilings and finishes took place and replacement of the same in accordance with approved design criteria, drawings and specifications.